| Due Date | Utilities & Proceeding | Regulatory Item | Order/Letter |
| 2007/12/13 |
x UNOCAL - Disposition of Aitken Creek Gas Storage - COMPLETED
Unocal Canada Limited ~ Disposition of Interest in the Aitken Creek Storage Facility to Aitken Creek Gas Storage ULC ~ Aitken Creek Gas Storage ULC Certificate of Public Convenience and Necessity Application and Application for an Exemption Order in respect of its Ownership and Operation of the Aitken Creek Storage Facility ~ Project No. 3698487 ~ Written Hearing
Panel: R. Hobbs
Lead Staff: B. Williston
Counsel: TBA
Hearing Location:
Date & Time:
@
Location:
,
,
| Applicants submit written Reply Comments to the Commission | G-143-07; L-97-07 |
| 2008/02/22 |
x BC Hydro - Rate Design Directives 26, 27, 28 on E-Plus - COMPLETED
BC Hydro January 24, 2008 Compliance filing with respect to Directives 26, 27 and 28 of the Phase I Rate Design Decision and an Application to amend Rate Schedules 1105, 1205, 1206, 1207 and to cancel Rate Schedule 1277 pursuant to Sections 58 and 60 of the Utilities Commission Act ~ Project No. 3698501
Lead Staff: Eileen Cheng
Panel: Pullman, O'Hara, Milbourne
Counsel: G. Fulton
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro to file Reply Submissions | G-16-08 |
| 2008/10/07 |
TGI TGVI TGW 2008 Resource Plan
Terasen Gas Inc. and Terasen Gas (Vancouver Island) Inc. and Terasen Gas (Whistler) ~ 2008 Resource Plan ~ Project No. #3698520 ~ Written Proceeding
Panel: A.W.K. Anderson, A. Rhodes
Lead Staff: G. Isherwood
Staff: B. Brownell, A. Kleinschmidt
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Final Submission | G-120-08 |
| 2008/10/15 |
TGI TGVI TGW 2008 Resource Plan
Terasen Gas Inc. and Terasen Gas (Vancouver Island) Inc. and Terasen Gas (Whistler) ~ 2008 Resource Plan ~ Project No. #3698520 ~ Written Proceeding
Panel: A.W.K. Anderson, A. Rhodes
Lead Staff: G. Isherwood
Staff: B. Brownell, A. Kleinschmidt
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-120-08 |
| 2008/10/24 |
TGI TGVI TGW 2008 Resource Plan
Terasen Gas Inc. and Terasen Gas (Vancouver Island) Inc. and Terasen Gas (Whistler) ~ 2008 Resource Plan ~ Project No. #3698520 ~ Written Proceeding
Panel: A.W.K. Anderson, A. Rhodes
Lead Staff: G. Isherwood
Staff: B. Brownell, A. Kleinschmidt
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Reply Submission | G-120-08 |
| 2008/10/27 |
BCTC - Central Vancouver Island CPCN
BCTC - Central Vancouver Island Transmission Project ~ Certificate of Public Convenience and Necessity
Panel: A.J. Pullman
M. Harle
Lead Staff: B. Williston
Staff: T. Roberts
Consultants: G. Isherwood
Hearing Location:
Date & Time:
@
Location:
,
,
| BCTC Written Reply Submission | G-137-08; A-14 |
| 2008/11/06 |
TGI-Fort Nelson Area ~ 2009 Revenue Requirements & Schedule of Rates
TGI ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 for the Fort Nelson Service Area and 2009 Revenue Requirements ~ Project No 3698525
Panel: P. Nakoneshney
Lead Staff: S. Mah
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission IR No. 2, if necessary | G-144-08; G-153-08 |
| 2008/11/07 |
TGI-TGVI Energy Efficiency and Conservation Programs
TGI-TGVI ~ Application for Energy Efficiency and Conservation Programs ~ Project No. 3698512 ~
Panel: K. Anderson, A. Rhodes
Lead Staff: J.W. Fraser
Staff: T. Roberts, G. Isherwood, D. Chong, E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| Responses to Information Requests by Intervenors | G-130-08 |
| 2008/11/07 |
TGI 2008 Annual Review
TGI ~ 2008 Annual Review ~ Project No # 3698520
Panel:
Lead Staff: S. Sue/B. Grant
Staff: P. Nakoneshny, S. Mah, B. Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| Joint TGI 2008 Annual Review / TGVI 2008 Settlement Update Meeting | G-142-08 |
| 2008/11/07 |
TGVI 2008 Settlement Update
TGVI ~ 2008 Settlement Update Meeting and 2009 Revenue Requiements ~ Project No. 3698527
Panel: A. Rhodes, P. Vivian
Lead Staff: TBD
Staff: P. Nakoneshny
Hearing Location:
Date & Time:
@
Location:
,
,
| Joint TGI 2008 Annual Review / TGVI 2008 Settlement Update Meeting | G-143-08 |
| 2008/11/07 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Request No. 1 to BC Hydro | G-148-08; G-154-08; A-10 |
| 2008/11/12 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| BCUC IR #2 and Intervenor IR #1 | G-161-08 |
| 2008/11/13 |
TGI-Fort Nelson Area ~ 2009 Revenue Requirements & Schedule of Rates
TGI ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 for the Fort Nelson Service Area and 2009 Revenue Requirements ~ Project No 3698525
Panel: P. Nakoneshney
Lead Staff: S. Mah
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Fort Nelson Response to Commission IR No. 2 | G-144-08; G-153-08 |
| 2008/11/17 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Participant Assistance/Cost Award Budgets | G-161-08 |
| 2008/11/19 |
TGI-TGVI Energy Efficiency and Conservation Programs
TGI-TGVI ~ Application for Energy Efficiency and Conservation Programs ~ Project No. 3698512 ~
Panel: K. Anderson, A. Rhodes
Lead Staff: J.W. Fraser
Staff: T. Roberts, G. Isherwood, D. Chong, E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Final Submissions | G-130-08 |
| 2008/11/19 |
Central Coast Power Sale of Utility Assets to Boralex Ocean Falls Partnership
Central Coast Power Corporation and Boralex Ocean Falls Limited Partnership ~ Project No. 3698513 ~ Order No. G-121-08 ~ Application for Approval of the Sale and Disposition of Utility Assets of Central Coast Power Corporation to Boralex Ocean Falls Limited Partnership
Panel: P. Vivian
Lead Staff: S. Sue
Staff: P. Nakoneshny, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| Submissions of the participants on the leave application | L-54-08 |
| 2008/11/19 |
TGI 2008 Annual Review
TGI ~ 2008 Annual Review ~ Project No # 3698520
Panel:
Lead Staff: S. Sue/B. Grant
Staff: P. Nakoneshny, S. Mah, B. Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI & TGVI responses to Undertakings | G-142-08 |
| 2008/11/19 |
TGVI 2008 Settlement Update
TGVI ~ 2008 Settlement Update Meeting and 2009 Revenue Requiements ~ Project No. 3698527
Panel: A. Rhodes, P. Vivian
Lead Staff: TBD
Staff: P. Nakoneshny
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI & TGVI responses to Undertakings | G-143-08 |
| 2008/11/19 |
BC Hydro - RS 1289 Net Metering Repricing
BC Hydro and Power Authority Rate Schedule Net Metering Repricing Application dated October 3, 2008 ~ Project #3698522 ~ Written Public Hearing
Panel: TBD
Lead staff: TRoberts
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Information Requests to BC Hydro | G-170-08 |
| 2008/11/19 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Registration of Intervenors and Interested Parties | G-159-08 |
| 2008/11/20 |
BC Hydro - RS 1289 Net Metering Repricing
BC Hydro and Power Authority Rate Schedule Net Metering Repricing Application dated October 3, 2008 ~ Project #3698522 ~ Written Public Hearing
Panel: TBD
Lead staff: TRoberts
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro responses to BCUC Information Requests | G-158-08; G-170-08 |
| 2008/11/21 |
BC Hydro - 2008 LTAP
BC Hydro 2008 Long Term Acquisition Plan dated June 12, 2008 ~ Project No. #3698514
Panel: T. Pullman, B. Milbourne, M. Harle
Lead Staff: E. Cheng
Staff: B. Williston, P. Nakoneshny, T. Berry, G. Isherwood,
Hearing Location:
Date & Time:
@
Location:
,
,
| BCUC, BC Hydro & Intervenor IRs on Intervenor Evidence | G-126-08 |
| 2008/11/21 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro responses to Intervenor IR #1 | G-148-08; G-154-08; A-10 |
| 2008/11/21 |
PNG & LNG Partners - Term Sheet Application
PNG ~ Application for Approval of a Term Sheet between PNG and LNG Parners LLC ~ Project No. 3698532
Panel: TBD
Lead Staff: T. Roberts
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| PNG Final Submissions | G-163-08 |
| 2008/11/21 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGW Responses to BCUC/Intervenor IR #1 | G-152-08; G-169-08 |
| 2008/11/21 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Information Requests to Stargas | G-159-08 |
| 2008/11/24 |
Central Coast Power Sale of Utility Assets to Boralex Ocean Falls Partnership
Central Coast Power Corporation and Boralex Ocean Falls Limited Partnership ~ Project No. 3698513 ~ Order No. G-121-08 ~ Application for Approval of the Sale and Disposition of Utility Assets of Central Coast Power Corporation to Boralex Ocean Falls Limited Partnership
Panel: P. Vivian
Lead Staff: S. Sue
Staff: P. Nakoneshny, S. Mah
Hearing Location:
Date & Time:
@
Location:
,
,
| Written Reply Submissions of the Heiltsuk | L-54-08 |
| 2008/11/26 |
TGI 2008 Annual Review
TGI ~ 2008 Annual Review ~ Project No # 3698520
Panel:
Lead Staff: S. Sue/B. Grant
Staff: P. Nakoneshny, S. Mah, B. Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| Participants comments to TGI & TGVI | G-142-08 |
| 2008/11/26 |
TGVI 2008 Settlement Update
TGVI ~ 2008 Settlement Update Meeting and 2009 Revenue Requiements ~ Project No. 3698527
Panel: A. Rhodes, P. Vivian
Lead Staff: TBD
Staff: P. Nakoneshny
Hearing Location:
Date & Time:
@
Location:
,
,
| Participants comments to TGI & TGVI | G-143-08 |
| 2008/11/26 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FBC Response to Information Requests | G-161-08 |
| 2008/11/26 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Commission & Intervenors IR#2 to BC Hydro | G-148-08; G-154-08; A-10 |
| 2008/11/27 |
BC Hydro - 2008 LTAP
BC Hydro 2008 Long Term Acquisition Plan dated June 12, 2008 ~ Project No. #3698514
Panel: T. Pullman, B. Milbourne, M. Harle
Lead Staff: E. Cheng
Staff: B. Williston, P. Nakoneshny, T. Berry, G. Isherwood,
Hearing Location:
Date & Time:
@
Location:
,
,
| Second Procedural Conference | A-6 |
| 2008/11/27 |
TGI-Fort Nelson Area ~ 2009 Revenue Requirements & Schedule of Rates
TGI ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 for the Fort Nelson Service Area and 2009 Revenue Requirements ~ Project No 3698525
Panel: P. Nakoneshney
Lead Staff: S. Mah
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Ft. Nelson Reply Comments | G-153-08 |
| 2008/11/28 |
TGI-TGVI Energy Efficiency and Conservation Programs
TGI-TGVI ~ Application for Energy Efficiency and Conservation Programs ~ Project No. 3698512 ~
Panel: K. Anderson, A. Rhodes
Lead Staff: J.W. Fraser
Staff: T. Roberts, G. Isherwood, D. Chong, E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-130-08 |
| 2008/12/01 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Filing of Independent Engineering Report | G-166-08 |
| 2008/12/01 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Stargas Resposnes to Information Requests | G-159-08 |
| 2008/12/02 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Community Input Session | G-161-08 |
| 2008/12/02 |
ICBC Proposal Plan for Independent Third Party Review
ICBC ~ Filing respecting a Proposal Plan for an Independent Third Party Review of ICBC's Financial Allocation Methodology (Regional Claims Allocation Order G-73-08) ~ Project #3698536
Panel: P. Vivian
Lead Staff: TBA
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Registration deadline for Intervenors & Interested Parties | G-167-08 |
| 2008/12/03 |
TGI 2008 Annual Review
TGI ~ 2008 Annual Review ~ Project No # 3698520
Panel:
Lead Staff: S. Sue/B. Grant
Staff: P. Nakoneshny, S. Mah, B. Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI & TGVI Reply comments | G-142-08 |
| 2008/12/03 |
TGVI 2008 Settlement Update
TGVI ~ 2008 Settlement Update Meeting and 2009 Revenue Requiements ~ Project No. 3698527
Panel: A. Rhodes, P. Vivian
Lead Staff: TBD
Staff: P. Nakoneshny
Hearing Location:
Date & Time:
@
Location:
,
,
| TGI & TGVI Reply comments | G-143-08 |
| 2008/12/04 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Information Requests to FortisBC | G-166-08 |
| 2008/12/05 |
TGI-TGVI Energy Efficiency and Conservation Programs
TGI-TGVI ~ Application for Energy Efficiency and Conservation Programs ~ Project No. 3698512 ~
Panel: K. Anderson, A. Rhodes
Lead Staff: J.W. Fraser
Staff: T. Roberts, G. Isherwood, D. Chong, E. Cheng
Hearing Location:
Date & Time:
@
Location:
,
,
| Terasen Reply Submissions | G-130-08 |
| 2008/12/05 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FBC Final Submission | G-161-08 |
| 2008/12/05 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro Response to BCUC and Intervenors Request No. 2 | G-148-08; G-154-08; A-10 |
| 2008/12/05 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| BCUC & Intervenor IR No. 2 | G-169-08 |
| 2008/12/05 |
BC Hydro - RS 1289 Net Metering Repricing
BC Hydro and Power Authority Rate Schedule Net Metering Repricing Application dated October 3, 2008 ~ Project #3698522 ~ Written Public Hearing
Panel: TBD
Lead staff: TRoberts
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro responses to Intervenor Information Requests | G-170-08 |
| 2008/12/07 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Stargas Written Final Submission | G-159-08 |
| 2008/12/09 |
ICBC Proposal Plan for Independent Third Party Review
ICBC ~ Filing respecting a Proposal Plan for an Independent Third Party Review of ICBC's Financial Allocation Methodology (Regional Claims Allocation Order G-73-08) ~ Project #3698536
Panel: P. Vivian
Lead Staff: TBA
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Workshop commencing at 9:00 am | G-167-08 |
| 2008/12/10 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC Responses to Information Request | G-166-08 |
| 2008/12/12 |
TGI 2008 Annual Review
TGI ~ 2008 Annual Review ~ Project No # 3698520
Panel:
Lead Staff: S. Sue/B. Grant
Staff: P. Nakoneshny, S. Mah, B. Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| Anticipated Commission Decisions | G-142-08 |
| 2008/12/12 |
TGVI 2008 Settlement Update
TGVI ~ 2008 Settlement Update Meeting and 2009 Revenue Requiements ~ Project No. 3698527
Panel: A. Rhodes, P. Vivian
Lead Staff: TBD
Staff: P. Nakoneshny
Hearing Location:
Date & Time:
@
Location:
,
,
| Anticipated Commission Decisions | G-143-08 |
| 2008/12/12 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-161-08 |
| 2008/12/12 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Submission of Intervenor Evidence | G-154-08; A-10; A-11 |
| 2008/12/12 |
BC Hydro - RS 1289 Net Metering Repricing
BC Hydro and Power Authority Rate Schedule Net Metering Repricing Application dated October 3, 2008 ~ Project #3698522 ~ Written Public Hearing
Panel: TBD
Lead staff: TRoberts
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-158-08; G-170-08 |
| 2008/12/12 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenors Written Final Submissions | G-159-08 |
| 2008/12/15 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Participants File Written Evidence | G-166-08 |
| 2008/12/17 |
STARGAS - Supply & Services Agreement with DEML
Stargas Utilities Ltd. Application dated August 31, 2008 - Natural Gas Supply and Management Services Agreement with Direct Energy Marketing Limited
Panel: Thurs AM Meeting
Lead Staff: JBW
Hearing Location:
Date & Time:
@
Location:
,
,
| Stargas Reply Submission | G-159-08 |
| 2008/12/18 |
BC Hydro - 2008 LTAP
BC Hydro 2008 Long Term Acquisition Plan dated June 12, 2008 ~ Project No. #3698514
Panel: T. Pullman, B. Milbourne, M. Harle
Lead Staff: E. Cheng
Staff: B. Williston, P. Nakoneshny, T. Berry, G. Isherwood,
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor responses to BCUC, BC Hydro and Intervenors IRs | G-126-08 |
| 2008/12/18 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Information Requests on Participant Written Evidence | G-166-08 |
| 2008/12/19 |
FortisBC CPCN Benvoulin Substation Project
FBC ~ Application for a Certificate of Public Convenience and Necessity for Benvoulin Substation Project ~ Project No. 3698529
Panel: L. O'Hara, P. Vivian, D. Cote
Lead Staff: B. Williston
Staff: P. Nakoneshny, T. Roberts, R. Stubbings
Hearing Location:
Date & Time:
@
Location:
,
,
| FBC Reply Submission | G-161-08 |
| 2008/12/19 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BCUC, Applicant & Intervenor IR#3 on Intervenor Evidence | G-154-08; A-10; A-11 |
| 2008/12/19 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGW response to BCUC & Intervenor IR #2 | G-169-08 |
| 2008/12/19 |
BC Hydro - RS 1289 Net Metering Repricing
BC Hydro and Power Authority Rate Schedule Net Metering Repricing Application dated October 3, 2008 ~ Project #3698522 ~ Written Public Hearing
Panel: TBD
Lead staff: TRoberts
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro Final Submission | G-158-08; G-170-08 |
| 2008/12/22 |
BC Hydro - 2008 LTAP
BC Hydro 2008 Long Term Acquisition Plan dated June 12, 2008 ~ Project No. #3698514
Panel: T. Pullman, B. Milbourne, M. Harle
Lead Staff: E. Cheng
Staff: B. Williston, P. Nakoneshny, T. Berry, G. Isherwood,
Hearing Location:
Date & Time:
@
Location:
,
,
| Direct Testimony and Rebuttal Evidence, if any | G-126-08 |
| 2008/12/23 |
ICBC Proposal Plan for Independent Third Party Review
ICBC ~ Filing respecting a Proposal Plan for an Independent Third Party Review of ICBC's Financial Allocation Methodology (Regional Claims Allocation Order G-73-08) ~ Project #3698536
Panel: P. Vivian
Lead Staff: TBA
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Submissions on the Filing | G-167-08 |
| 2008/12/24 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| Response to Information Requests | G-166-08 |
| 2008/12/30 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor resp to BCUC, Applicant and Intervenor IR#3 | G-154-08; A-10; A-11 |
| 2009/01/05 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| CCQRLR and QRRA Final Submissions | G-166-08 |
| 2009/01/08 |
BC Hydro - 2008 LTAP
BC Hydro 2008 Long Term Acquisition Plan dated June 12, 2008 ~ Project No. #3698514
Panel: T. Pullman, B. Milbourne, M. Harle
Lead Staff: E. Cheng
Staff: B. Williston, P. Nakoneshny, T. Berry, G. Isherwood,
Hearing Location:
Date & Time:
@
Location:
,
,
| Oral Public Hearing commences | G-126-08 |
| 2009/01/09 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro Final Submissions | G-148-08; G-154-08; A-10; A-11 |
| 2009/01/09 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| FortisBC and other Participants Final Submissions | G-166-08 |
| 2009/01/09 |
ICBC Proposal Plan for Independent Third Party Review
ICBC ~ Filing respecting a Proposal Plan for an Independent Third Party Review of ICBC's Financial Allocation Methodology (Regional Claims Allocation Order G-73-08) ~ Project #3698536
Panel: P. Vivian
Lead Staff: TBA
Staff:
Hearing Location:
Date & Time:
@
Location:
,
,
| ICBC Reply Submissions | G-167-08 |
| 2009/01/14 |
FortisBC - Ellison Substation Reconsideration
Applications for Reconsideration of Commission Orders C-04-07 and G-75-07 from the Concerned Citizens of Quail Ridge and Lochrem Road (“CCQRLR”) and Quail Ridge Residents Association (“QRRA”)
Panel: TBD
Lead Staff: TBD
Staff: TBD
Hearing Location:
Date & Time:
@
Location:
,
,
| CCQRLR and QRRA Reply Submissions | G-166-08 |
| 2009/01/16 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Final Submissions | G-148-08; G-154-08; A-10; A-11 |
| 2009/01/23 |
BC Hydro - Power Purchase Agreement (RS#3808)
BC Hydro ~ Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement ~ Project No. 3698531
Panel: L. O'Hara, P. Vivian, A. Rhodes
Lead Staff: D. Flintoff
Staff: J. Fraser
Hearing Location:
Date & Time:
@
Location:
,
,
| BC Hydro Reply Submission | G-148-08; G-154-08; A-10; A-11 |
| 2009/01/23 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGW Submissions | G-169-08 |
| 2009/01/30 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| Intervenor Submissions | G-169-08 |
| 2009/02/06 |
TGW ~ 2009 ROE & Capital Structure
TGW ~ Application for Approval to Amend its Schedule of Rates Effective January 1, 2009 and for a Return on Equity and Capital Structure ~ Written Hearing ~ Project #3698533
Panel: TBD
Lead Staff: Sue/Grant
Staff: Nakoneshny, Mah, Brownell
Hearing Location:
Date & Time:
@
Location:
,
,
| TGW Reply | G-169-08 |